This pane contains general information for the selected planning period.
Row | Description | Notes |
Projected Hours | System calculation of the number of hours that should be scheduled for the day based on the imported events and all related tasks. | Read-only. |
Scheduled Hours | Number of hours currently scheduled for the day. | Read-only. |
Net Excess / Shortfall | The difference between Scheduled Hours and Projected Hours (Scheduled Hours − Projected Hours).
| Read-only. |
Optional Pre-work | Number of hours of work content planned for a specific day that could be completed on earlier days. | Read-only. |
Optional Post-work | Number of hours of work content planned for a specific day that could be completed on later days. | Read-only. |
Distributed Percentage | Percentage of work content that has been distributed to the planned shifts. | Read-only. |
Undistributed Hours | Number of hours of work content that is not distributed to the planned shifts. | Read-only. |