Copying shifts in Timeline Scheduling
You can use your mouse and keyboard to copy shifts in both the Jobs and Employees views on the Timeline Scheduling screen.
Copying a single shift
- In the schedule pane, hold down the Ctrl key and drag a shift bar to where you want to place the copy.
The copy of the shift appears on the schedule.Â
Copying multiple shiftsÂ
- In the schedule pane, select a group of shifts by doing the following:
- Hold down the Ctrl key and drag over a group of shifts.
The borders of the selected shifts are outlined.
Or - Hold down the Ctrl key and click on each shift you want to move.
The borders of the selected shifts are outlined.Â
- Hold down the Ctrl key and drag over a group of shifts.
- Drag the selected group of shifts up or down on the schedule pane.
The copies of the shifts appear on the schedule.Â