Labor Effectiveness Report
The Labor Effectiveness report provides a weekly summary of the same information that is displayed in the Daily Operating report. The report calculates the variance in projected and actual volumes, as well as job forecast and scheduled variances.
There might be different units of measurement associated with work that is produced before the schedule day. Although daily figures might be distorted, they will balance out over the course of the week. An example of this type of situation is banquet production. Sometimes productions take place 2 to 3 days before to the function, thus the hours for the function day might be lower than standard, and days prior might be higher.
You can also run the Labor Effectiveness report for a shorter period time to assist in evaluating overtime usage by department or job. This report summarizes by department while still listing individual jobs.
Report Options
Option | Description |
Mode | Determine whether the information is filtered by Division/Department or by Operating Code.
|
Start Date/End Date | Designate the first day and last day that data should be collected for the report. Note the green arrow icon resets the dates to the previous period. |
Scheduled Hours | Adds a column to the report that lists scheduled hours. |
Breakdown Hours | If selected, Worked Hours are organized by shift categories:
|
Hours/FTEs | Select to display units as hours or FTEs (Full Time Equivalents). See Units displayed as FTEs. Determined by dividing actual hours by 40. The resultant value tells you how many people worked in this job (or department or division) if each employee worked 40 hours. If the report period is greater than seven days, LMS will divide the number of days by seven to arrive at a standard week for use in calculating FTE's |
Fields on the Labor Effectiveness report - Hours selected
Field | Description |
Weekly FTE | Full Time Equivalents—Represents the total hours for the report divided by 40. The resultant value tells you how many people worked in this job (or department or division) if each employee worked 40 hours. If the report period is greater than seven days, RMS will divide the number of days by seven to arrive at a standard week for use in calculating FTEs. This column displays how many FTEs there were this week. |
Worked Hours | Displays the actual worked hours that come from the property's time and attendance system or employee time records. |
Standard Hours | Displays the hours that should have been used based on the actual volumes relative to the standards that were set up. |
Scheduled Hours | Displays the hours from your final schedule as entered in RMS . |
Projected Hours | Displays the hours that were scheduled and edited in the system when the system administrator closed the schedules for further editing. |
Hours Variance | Displays the variance between actual hours and standard hours. |
Variance % | Displays the percent achievement relative to standard. |
Actual Costs | Displays the results of multiplying the actual hours by the avg. wage(s). |
Standard Costs | Displays the results of multiplying the standard hours by the avg. wage(s). |
Dollars Costs | Displays the variance between actual dollars and standard dollars. |
Overtime Hours | Displays the overtime hours for the selected job, department, or division. |
OT Pay | Displays the results of multiplying the number of overtime hours worked by the appropriate overtime pay rate. |
Fields on the Labor Effectiveness report - FTEs selected
Field | Description |
Worked FTEs | Displays the actual number of FTEs worked. |
Standard FTEs | Displays the FTEs that are based on the actual volumes relative to the standards that were set up. |
Schedule FTEs | Displays the FTEs from your final schedule as entered in LMS. |
Projected FTEs | Displays the FTEs that are based on the original forecast volumes for the designated relative to the standards that were set up. |
FTE Variance | Displays the variance between actual FTEs and standard FTEs. |
Variance % | Displays the percent achievement relative to standard. |
Actual Costs | Displays the results of multiplying the actual hours by the avg. wage(s). |
Standard Costs | Displays the results of multiplying the standard hours by the avg. wage(s). |
Costs Variance | Displays the variance between actual dollars and standard dollars. |
Overtime Hours | Displays the overtime hours for the selected job, department, or division. |