The Work Content view in Timeline Scheduling uses color-coded bars to illustrate the type and duration of work content.

Color codes in the Work Content view

ColorDescriptionNotes

Light green

Setup window of opportunity - The amount of time required to prepare for the work. 

Green

Setup - The amount of time required to complete setup work. 

Light red

Teardown window of opportunity - The amount of time required to prepare for teardown work. 

Red

Teardown - The amount of time required to complete teardown work. 

Light orange

Multi-event window of opportunity - The amount of time required to prepare for multi-event work. 

Orange

Multi-event - The amount of time required to complete multi-event work. 

Dark gray

Actual amount of time - Preferred time to complete an work content.Applies to all types of work content.