_WATSON-27231 FI Reporter
27231
Summary | In Reporter, the option selected in the Week End field of the Weekly Schedule report configuration screen moves forwards and backwards in increments of one week, as expected. |
---|---|
Description | In some instances of previous Reporter releases, the Week End field of the Weekly Schedule report configuration screen did not update correctly. Instead of moving forwards and backwards a full week, the date occasionally moved in increments of 6 days. |
Solution | The Reporter software has been updated so that the option selected in the Week End field selection of the Weekly Schedule report configuration screen moves forwards and backwards in increments of one week, as expected. |
Affected RMS  versions: | Version 10.8 and later. |