Re-Calculating the 30-60-90 Forecast

After you have entered all your data in the Period or Daily tabs, you will need to re-calculate the budget.

  1. Select Re-Calculate Forecast from the Related Tasks drop-down menu.
  2. If desired, choose the appropriate Division/Department/Job and Standard Set. See note below.
  3. Click OK. A progress bar appears. Please be patient as this process can take awhile to complete. When complete, you will be returned to the main screen.

    Most of the time you will leave Division, Department and Job set to All. However, if you know that you made changes to a KBI that only applies to a certain area of the job class tree, choose the specific Division/Department/Job that was affected. The re-calculation time is greatly reduced.

    After clicking OK, please be patient as these calculations may take a while.