This report shows totals by job per week, and indicates what should have been staffed versus was was actually staffed, as well as what was forecasted forecast and scheduled. (Forecast hours come from the original forecast hours that LMS generated based on the forecasted forecast volumes for the week.) KBIs associated with that job are also displayed to give you a point of reference.
...
Option | Description | Notes | ||||||
Mode | Determine whether the information is filtered by Division/Department or by Operating Code.
| |||||||
Period End Date | Designate the last day that data should be collected for the report. | |||||||
Scheduled Hours | Adds a column to the report that lists scheduled hours. | |||||||
Breakdown Hours | Actual Hours are organized by shift categories.
| |||||||
Show Standard Set | If selected, the report displays which standard set was used for each day of the week to project hours and which standard set was used to used to generate standard hours. | Only applicable if dynamically applied standard sets are configured. | ||||||
KBI Variance | Display KBI Variance in the report. | |||||||
Show Standards Based KBIs | Display Standards Based KBIs in the report. | |||||||
Daily Hours | Display units as hours in a daily format. | |||||||
Weekly Hours | Display units as hours in a weekly format. | |||||||
Weekly FTEs | Display units as full-time equivalents (divide actual hours by 40) in a weekly format. The resultant value tells you how many people worked in this job (or department or division) if each employee worked 40 hours. If the report period is greater than seven days,
|
...
- Choose Labor from the Reports menu.
- Click Analysis and select Weekly Labor Summary. The Options dialog box appears.
- Select a Mode.
- If Division/Department is selected, choose the appropriate Division, Department and Summarize By options.
- If Operating Code is selected, choose the approriate appropriate operation.
- Enter the Start Date/End Date by entering a date, clicking on the calendar icon and selecting a date, or using the date forward and date backward arrows.
- Select or de-select Scheduled Hours.
- Select either Daily Hours, Weekly Hours or Weekly FTEs.
- Click the Run icon. The report is displayed.
...
Term | Definition | Notes | |
Department/Division Totals | Summarizes data for the whole division/department. | ||
KBIsApplied KBIs | Actual and forecast KBI for each department. | Appears only if Show Standards Based KBIs is selected in the configuration screen. | |
Standard sets | Standard set used for each day of the week:
| Only applicable if dynamically applied standard sets are configured. | |
Forecast | Displays the manager's Projected | Hours that should be scheduled based on the forecast business volume. | |
Scheduled | Displays the hours Hours from your schedule. | ||
Actual | Displays the hours Hours that come from your your property's Time and Attendance system or employee time records. | ||
Standard | Displays the hours that are Hours that should have been used based on the actual volumes relative to the standards that were set up. | ||
Variance % | Displays the difference between Forecast hours and Actual Difference between standard hours and actual hours. |
...