Fields on the Generate Projected Hours dialog box
Field | Description | Notes |
Division | Select a division from the drop-down list. | |
Department | Select a department from the drop-down list. | |
Job | Select a job from the drop-down list. | |
Rotate Days Off | Select if the KBI data should be recalculated because changes were made after the schedule was generated. | This check box appear only if you have Administrator permission. |
Log Work Calculations | Sends information to a database where Tech Support can troubleshoot internal calculations. | |
Start Date | Date on which to start generating the projected hours. | |
End Date | Date on which to stop generating the projected hours. | |
Buttons | ||
OK | Generates the schedule. | |
Cancel | Cancels the task and the dialog box closes. |
Running the Re-Project Labor task
...